Frequently Asked Questions
Has the Howard – Solstice 765 kV transmission line been approved?
Yes. On September 11, 2026, the Public Utility Commission of Texas approved the joint application of AEP Texas and CPS Energy in Docket No. 59336 and adopted Route 4 Modification 1. The line runs roughly 370 miles from CPS Energy’s Howard Substation southwest of San Antonio to AEP Texas’ Solstice Substation near Fort Stockton, with a planned in-service date of fall 2030.
Which Texas counties does the approved route cross?
As approved, the line runs through or near Atascosa, Bandera, Bexar, Crockett, Edwards, Kerr, Kinney, Medina, Pecos, Real, Sutton, Terrell, Uvalde and Val Verde Counties. Being in one of these counties does not mean the line crosses your land, and not being contacted yet does not mean it does not.
How wide is the easement and how tall are the structures?
AEP Texas plans self-supporting steel lattice structures and guyed structures, typically 140 to 160 feet tall and spaced about 1,400 feet apart, within a permanent easement typically 200 feet wide. A 160-foot structure is about as tall as a 13-story building.
Can a Texas landowner stop the transmission line?
No. Companies with eminent-domain authority can take property for public use with or without the owner’s consent. What a landowner can control is the amount of compensation and the terms of the easement.
What counts as adequate compensation under Texas law?
Adequate compensation is more than the value of the acreage inside the easement. It can include the value of the land taken, the loss in value to the remainder of the property, damage to farming and ranching operations and access, future development restrictions, and construction and maintenance damages.
What should I do when a right-of-way agent contacts me?
Be courteous, write down the date, the agent’s name and what was said, ask for the easement document itself rather than just the offer letter, and photograph your property. Do not sign a survey permission or right-of-entry form before it has been reviewed, do not discuss numbers, and do not cash a check.
What happens if I cannot reach an agreement with the utility?
The utility can file a condemnation petition in the county where the property is located. Three special commissioners who own land and live in that county hold a hearing and set an award. Either side may object to the award and try the adequate-compensation question to a jury in that same county.
What does Harrison Davis charge to represent a landowner?
Harrison Davis represents landowners on a contingency fee basis with no up-front fees or costs. The fee is based only on the amount recovered above the utility’s initial written offer. If the firm does not increase the compensation, the landowner owes no attorney’s fees or case expenses.
If Your Land Is on or Near the Approved Route, We Can Help
You don’t have to fight this alone—and you shouldn’t. Contact Harrison Davis for a free, no-obligation consultation.
We represent landowners on a contingency fee basis, with no up-front fees or costs. Our fee is based only on the amount we recover above the utility’s initial written offer. If we don’t increase your compensation, you owe no attorney’s fees or case expenses.
Call (800) 460-2756, or toll-free (800) 460-2756, or fill out our online intake form and one of our condemnation trial attorneys will contact you.